Operation And Maintenance Of Motor

Checklist Of Motor running operation;

1 The Field Operator should not start the operation until the notice has been given.

2 The electric power of the motor is stopped by the Shift Chief-Operator and above, and is signed on the operation ticket.

3 The motor start /stop should and operator must monitor the electrical parameter. Operator should record the motor stop, start stop time and cause details.

4 The starting times of the motor should comply with the requirements of the manufacturer, and if the manufacturer fails to make such provisions, the following provisions shall be observed:


Operation And Maintenance Of Machinery;


Squirrel cage rotor motor in normal cold state (core temperature below 50 DEG C) to start two times, each time interval of not less than 5 minutes, allowed to start once in the hot state, only in dealing with the accident and the start time is not more than 2 seconds to 3 seconds to start the motor, a. Do the dynamic balance test, the starting time interval is:

1- 500 kW motor should not be less than 2 hours.

2- 200 kW ~ 500 kW motor should not be less than 60 minutes

3- 200 kW motor should not be less than 30 minutes

5 For remote operation of the motor should carry out the external inspection by the Operator, notify the operator and stay near the accident button, until the speed goes up to the rated normal operation.

6 When starting the motor, the Operator shall monitor the ammeter reading. After the start of the motor should check whether the current indicator exceeds the rated value,review the motor body when in doubt and report the Shift supervisor.

7 Under normal circumstances the motor is not allowed to start with load.

Comments

Popular posts from this blog

What Is Pressure With Explanation

What Is Pressure With Explanation : Is usually going for you guys.  In the industry, it is also associated with the highest unit and pressure: be it a small industry, be it an ice or cement factory.  Earnings or a street house.  You will have Yashar everywhere.  It is very difficult to understand the  instruments that are broadcast without  understanding the pressure.  Pressure is considered to be the basic meter in the world of instruments. What is pressure?   In common place air pressure is called pressure.  It is given even in football.  Whether in the tire tube of small scale, motorcycle, car, etc.  And also falls into the category of pressure.  Even blowing through the mouth is considered stressful.  If you have heard.  Fill this car with 40 pounds of air.  Pound here means pound per square inch.  This is a unit of pressure.  This will be mentioned in detail.  The doctor advises some patients ...

Backwash Work Of Coal Water Treatment System

Backwash start and stop operation steps: 1 Confirm that the coal water treatment water equipment has stopped working 2 Open the slime water purifier backwash inlet valve, mud valve. 3 Start backwash pump until slime water purifier drain valve starts to drain water. 4 Stop the backwash pump, close the slime water purifier backwash inlet valve, mud valve. 5 Slowly open the backwash pump when the following three conditions, the coal slurry for back washing Coal For Water Purification 1) To purify the regular coal slurry backwash time (set 360 hours to wash once); 2) Coal slurry purifier No. 3 monitoring faucet water turbidity; 3) Water flowing through the return pipe of the coal waste water purifier. 4)The water turbidity for a long time can not meet the design requirements of water quality. Note: When the sewage pipe discharges, only the clear water is discharged, and when the sludge is not discharged, the purifier should be stopped immediately, and the purifier drain valve should be ope...

Most Important Checklist Of Work Permit Power Plants 2020

  Complete Fill Of The Working Ticket S ystem; The working ticket filling must use standard terminology, and equipment shall be indicated the name and number.  Arabic numerals (bus can use Roman numerals) are needed; Time is calculated at 24 h, year is filled in four digits, months, day, hour and minute are in digits. Working controller column: (also) the guardian, the working controller of a single task or more should be filled. Team column for A-team maintenance, the full name is filled; for several-team a comprehensive maintenance, the maintenance unit is filled. operation crew column: we should fill each staff's name for more than 10 people, we only fill in the name of 10 people,  with number (such as xxx, etc. For) other personal's  name should be into  the attached pages. The total number includes working controller, and the guardian shall be specified. Working location column: the specific location where maintenance equipment are.  Working content co...